Dear All
Many thanks for your responses.
Replies:
1. Checked the Valuation Variant and it has the right Costing sheet that I have created for the customer.
2. The material is not a transfer from any other plant becoz the customer has only one plant.
3. The valuation tab in CK11N shows the right costing sheet.
4. Fun here is the values of overhead is correctly showing as per my calculation in excel sheet, but only the cost element read is being incorrect (CE 9411112 should be shown in place of CE 9411110 and CE 9411142 in place of 9411140)
My wild guess is there any program to refresh the cache.
Do any of you see any other issue?